ETCS Ceneri Base Tunnel, Tender and Realisation Train Control and Signalling System

Tender specification, offer evaluation, assistance of detailed design, realisation and commissioning of the new train control and signalling system for the Ceneri base tunnel on behalf of AlpTransit Gotthard AG (ATG). Assistance to ATG in setting up, check and approval of the detailed design with the contractor. Assistance to ATG in supervising the assembly and installation of the signalling equipment (sampling inspection, tests, …) and preparation and execution of the commissioning. The project is carried out by a consortium under the lead of Emch+Berger AG Bern.

The works includes all signalling related systems on an ERTMS-basis in the perimeter of the project such as control and communication system, interlocking, ETCS/RBC and is embedded over special interfaces into other neighbouring signalling systems (conventional signalling systems).

Client

AlpTransit Gotthard AG, Lucerne

Period
2010
2021
Fields of activity
Infrastructure;Rail infrastructure;Mobility and traffic;Rail systems
Delivered services

Submission documents

Offer evaluation

Assistance during procurement

Supervising the contractor

Assistance to the Client (ATG)

Technical support

Project management

Verification of the RAMS process

Cost controlling

Specifications

Two separated running tunnels: 15.4 km

Train speed: 80-250 km/h

Headway: 3 min

Train control system: ETCS level 2

RBC with GSM-R interface: 1

Interlockings: 1

Balises: approx. 200

Central Control System: 1