Development of Advanced Traffic Management and Decision Support Functionality for Rail Networks

Infrastructure
Rail infrastructure
Mobility and traffic
Rail systems / traffic management systems (TMS)

Tender Specification

Tender Evaluation

Lead in Requirements Clarification

Lead in Process Design by means of a Process Lab

Review of System and Subsystem Requirements (approx. 3000 requirements)

Support of the Customer in Cases of Differences with the Suppliers

Elaboration of Business Change Documentation for the Customer

Alignment between Research and Supplier

Alignment between Banedanmark and DSB, the principal Operator of danish long distance passenger services

Elaboration of Detailed Use Cases

1990
2021

Test and Commissioning Activities in ETCS Signalling Projects

Infrastructure
Rail infrastructure
Mobility and traffic
Rail systems / traffic management systems (TMS)
Consultancy service for test and commissioning, including elaboration of related overall concepts.
Verification of Suppliers’ test and commissioning documents
Supervision of test and commissioning activities
2009
2017

ETCS Gotthard Base Tunnel, Detailed Design and Realisation Train Control and Signalling System

Infrastructure
Rail infrastructure
Mobility and traffic
Rail systems / traffic management systems (TMS)

Supervising the contractor

Assistance to the Client (ATG)

Technical support

Project management

Verification of the RAMS process

Cost controlling

2009
2011

ETCS Level 2 Denmark, Traffic Management

Infrastructure
Rail infrastructure
Mobility and traffic
Rail systems / traffic management systems (TMS)
Description of Customer’s service perception
Design of Traffic Management Processes
Description of roles of all the stakeholders and their representation on the TMS
Description of a proper Decision Support System
Outline the Workflow at the Control Centre
Setting up Interfaces to other systems
Overall design and configuration of Control Centre
2010
2021

ETCS Ceneri Base Tunnel, Tender and Realisation Train Control and Signalling System

Infrastructure
Rail infrastructure
Mobility and traffic
Rail systems / traffic management systems (TMS)

Submission documents

Offer evaluation

Assistance during procurement

Supervising the contractor

Assistance to the Client (ATG)

Technical support

Project management

Verification of the RAMS process

Cost controlling

2006
2021

Network wide renewal of signalling and traffic management systems

Infrastructure
Rail infrastructure
Mobility and traffic
Rail systems / traffic management systems (TMS)

Within the Rambøll-Atkins-Emch+Berger-Parsons joint venture, Emch+Berger has provided the following main services:

Feasibility study: leading the technical and safety work stream; provide input to many key findings on how to achieve such a large migration within a reasonable time frame without disturbing daily operations; setting up a model counting the new signalling assets as a basis for the budget

Procurement phase: Technical project management of the elaboration of the tender documents and the bid assessment, providing contents for several disciplines, writing of the bid assessment reports

Design phase: Key contribution to management of design and development; discipline leadership in traffic management, automated dispatching, timetabling, signalling design to capacity, development of use cases covering the entire railway operation, ETCS level 2, testing; management of project controls; key inputs to the identification of business changes within Banedanmark

2016

Operational scenarios for a new traffic management system in Norway

Infrastructure
Rail infrastructure
Mobility and traffic
Rail systems / traffic management systems (TMS)

Definition methodology and framework of the scenario development

Execution of workshops to identify the contents for the scenario description

Consultation of the customer organisational unit and revision of the description

2007
2015

Büttenberg Tunnel

Infrastructure
Road engineering
Underground construction / geotechnics
General project management
Planning through all project phases from concept to realisation
Tender process, bid evaluation and award of contract
Execution planning
Construction logistics and material management
Site management
2012
2013

Preliminary Design of Centralised Traffic Control System and operational rules

Infrastructure
Rail infrastructure
Mobility and traffic
Rail systems / traffic management systems (TMS)

Tender Specification

Tender Evaluation

Lead in Requirements Clarification

Lead in Joint Design (to converge and interface the two products)

Review of System and Subsystem Requirements (requirement specifications were delivered by the suppliers covering approx. 2000 requirements each)

Support oft he Customer in Cases of Differences with the Suppliers

Elaboration of Business Change Documentation for the Customer

2010
2011

Preliminary Project Tramway Tampere

Infrastructure
Rail infrastructure
Mobility and traffic
Public transport
Rail systems / traffic management systems (TMS)

Definition of targeted customer perception together with the client

Tram routing, evaluation of variants

Overall network concept

Shaping of stops and transfer stations, integration to streets

Cost calculation, effects on City development

Communication, involvement of the public

2009
2011

ETCS Level 2 Denmark, Submission Train Control and Signalling System

Infrastructure
Rail infrastructure
Mobility and traffic
Rail systems / traffic management systems (TMS)

Technical concepts

Conceptual timetable 2020

Requirements / specifications

Comprehensive technical requirements

Submission documents

Offer evaluation

2000
2011

Moutier Tunnel

Infrastructure
Road engineering
Underground construction / geotechnics
Preliminary study
Building project
Tender process
Execution planning
Construction supervision
2009
2010

ETCS Level 2 Denmark, Concept Timetable 2020

Infrastructure
Rail infrastructure
Mobility and traffic
Rail systems / traffic management systems (TMS)

Gather future concepts

Evaluate future pinch points

Set up detailed timetable for 2020

Benchmark trip time and interval

Define required headways

Define requirements toward TMS

Define infra extension modules

2008
2009

Olympic Games Sochi 2014 - Logistics

Infrastructure
Rail infrastructure
Development of logistic chains
Development of external transport modes
Risk analysis
Proposals to centralise the control and management of freight logistic systems
Proposals on common information environment
Proposals on a passenger transportation centre
2008
2009

Railway Connection Voronezh - New International Airport

Infrastructure
Rail infrastructure
Mobility and traffic
Rail systems / traffic management systems (TMS)
Proposal on transport system and organisation
Definition of different scenarios
Model assessment
Global cost estimation (LCC-basis)
Revenue estimation / phase
Assessment and development of a PPP approach
Proposal on project schedule
Elaboration on traffic planning during construction phases
2008
2009

SBB Bahnhof Lucerne Pedestrian Simulation

Infrastructure
Regional development & urban planning
survey pedestrian movement
development origin destination matrix
behavioural modelling
pedestrian movement
measures
2008
2009

SBB Bahnhof Lucerne Pedestrian Simulation

Infrastructure
Regional development & urban planning
survey pedestrian movement
development origin destination matrix
behavioural modelling
pedestrian movement
developments of measures
2004
2008

ETCS Gotthard Base Tunnel, Tender Train Control and Signalling System

Infrastructure
Rail infrastructure
Mobility and traffic
Rail systems / traffic management systems (TMS)

Signal plan

System layouts

Submission documents

Offer evaluation

Assistance during procurement

Document management

2005
2008

ETCS Level 2 Denmark, Preliminary Design Study and Migration Planning

Infrastructure
Rail infrastructure
Mobility and traffic
Rail systems / traffic management systems (TMS)

Generation of the technical data base

Evaluation of available technology

Development of appropriate models for quantification

Development of Migration-Scenarios

Development of maintenance models

Assistance in cost modelling

Market surveys

2001
2008

Wankdorfplatz

Infrastructure
Civil engineering structures
transport and logistic conception
conception of the construction progress
verification of the capacities
microscopic traffic simulation
traffic management
accompanying measures